High Pressure Polyurethane Machine
10 Views

Automatic PU Tire Production Line | Bicycle Solid Tires

A 24-station rotary configuration for molded PU bicycle and e-bike tires, combining metering, indexed tooling, curing and demolding. Material, tire geometry and validated timing define the selected production conditions.

Carousel Configuration

24 mold stations in the listed model.

Density Reference

350–450 kg/m³ in the brief; final material properties follow formulation trials.

Tooling Range

12–28 inch tire sizes in the configuration reference; tooling and rim fit are selected separately.

Production Timing

Establish entry-to-demold cycle, mold cavities and output interval for the selected tire.

Project-Specific Commissioning and Training
Bicycle and Light-Mobility Microcellular Tire Production

Product Overview

The HF-BIKE-CAROUSEL-24 reference configuration combines a 24-station indexed carousel with PU metering, mold handling, curing and demolding for specified bicycle tires. Select the formulation and tooling for the required geometry, rim interface and component properties.

The original brief lists a 45–60 second timing reference, but its timing endpoints are not verified. It is not used here to promise tires per shift or per day. Final throughput follows the validated entry-to-demold cycle, mold cavities, output interval, daily working hours and downstream operations.

Product Overview

Production Workflow

Prepare the Mold

Prepare molds and the selected release-agent arrangement for the formulation.

Meter and Fill

Coordinate material metering, mixing and the shot with the selected tire tooling.

Cure and Index

Set mold-temperature control and indexed handling around validated demolding readiness.

Demold and Finish

Coordinate demolding, post-treatment, trimming and component inspection.

HF-BIKE-CAROUSEL-24

Technical Specifications

The listed model values are configuration references. Confirm the selected equipment schedule, material compatibility, timing definition and operating conditions in the technical agreement.

Technical ParameterHF-BIKE-CAROUSEL-24
ComponentsDual-Component (Polyol Blend, Formulated MDI)
Output Range (g/s)10 – 40 kg/min (Customizable)
Ratio Accuracy±0.5% (Closed-loop mass flowmeter feedback)
Power Supply380V / 50Hz, 3-Phase (Or 480V 60Hz Custom)
Working Pressure150 – 190 bar (High-pressure impingement)
Tank Capacity (L)250 L Stainless Steel Jacketed Tanks
Dimensions (L×W×H)Turntable Diameter: Approx. 7.5 Meters
Carousel Stations24 Mold Stations
Submitted Time Reference — Basis to Confirm45–60 s as listed in the brief. Confirm whether this applies to the full entry-to-demold cycle or an output interval before using it for capacity planning.
Tire Density Range350 – 450 kg/m³
Applicable Tire Sizes12" to 28" (Kids bikes to 700C e-bikes)

Key Features

Indexed Mold Handling

Coordinate the 24-station arrangement with filling, curing and demolding.

Formulation-Specific Tire Production

Select the material, density target, tire geometry and tooling together.

Component and Throughput Evaluation

Validate ride, wear, bonding and production timing for the selected tire; no maintenance-free life or universal output quantity is promised.

Frequently Asked Questions

How is production timing defined?
Cycle time means station entry to demolding. The original 45–60 second brief value has an unverified timing basis; confirm whether it is a full cycle or output interval. Parts per cycle follow the mold cavities, commonly one part per mold.
How is daily output planned?
Use the validated cycle and output interval, station utilization, mold cavities, daily working hours and downstream operations. State a one-shift or 10-hour planning schedule as applicable; do not convert the unverified timing reference into a guaranteed daily output.
How are comfort and durability assessed?
Evaluate the selected tire formulation, geometry and rim fit using the required rolling, vibration, load and wear criteria. Material density alone does not establish pneumatic-equivalent performance or service life.
Can colors and tire sizes be changed?
Color-feeding options and tooling are defined for the chosen material and size range. Confirm the equipment arrangement and changeover procedure in the project scope.