Offshore Marine Solar Frame Solution Banner background
Manufacturing Solutions

Offshore Marine Solar Frame Solution

Develop closed-box PU injection pultrusion for marine PV frame profiles with defined material and module tests.

Production objective

Heavy Structural Composite Framing for Offshore Floating Solar

Marine framing requires a specified profile, reinforcement, resin, connections and exposure assessment. Sealed resin conditioning and controlled injection support processing but do not independently establish corrosion life or electrical suitability. Metering pumps deliver the liquid resin components; they do not convey the continuous reinforcement.

Defined supply scope

Agree the conditioning, mixing and injection-box scope with the die, puller, dry-gas and cutting interfaces. Alternative glass, basalt or carbon reinforcement requires its own process and component review.

Inputs for process selection

Profile and connection drawings, fiber form/content basis, resin data, marine exposure, electrical requirements and line interfaces.

Equipment scope, retained factory interfaces and acceptance are agreed for the selected material and part. Agree the conditioning, mixing and injection-box scope with the die, puller, dry-gas and cutting interfaces. Alternative glass, basalt or carbon reinforcement requires its own process and component review.

Production route

Offshore Marine Solar Frame Workflow

Define profile and exposure → Prepare sealed resin supply → Inject and pultrude → Qualify profile and module. Define preparation, filling, cure and output timing separately for the selected configuration.

01

Define profile and exposure

Review frame section, connections, reinforcement and marine duty.

02

Prepare sealed resin supply

Establish conditioning, dry-gas and container-change procedures.

03

Inject and pultrude

Validate wet-out, die control and pulling for the selected fiber content.

Engineering inputs

Reference Solution Engineering Envelope

Existing configuration and test references. Equipment settings, material results and finished-assembly results are separate; apply each value only to its documented configuration and conditions.

ParameterValue / UnitApplicable Configuration / Conditions
Dosing Output Capacity1.0 to 10.0 kg/minHastelloy-coated servo-driven axial piston metering skid; supplied reference requiring configuration or test verification
Fluid Working Pressure12.0 to 15.0 MPaContinuous high-pressure closed-die impingement injection; supplied reference requiring configuration or test verification
Supported Fiber VolumeUp to 83% (Vf)E-CR glass, basalt, or carbon fiber dense structural packing; supplied reference requiring configuration or test verification
Salt Spray Durability LimitGreater than 9,000 hoursASTM B117 testing with flexural retention > 92%; supplied reference requiring configuration or test verification
Profile Wall ThicknessUp to 4.5 mm (Heavy section)Engineered for 4-meter wave slap and typhoon wind loads; supplied reference requiring configuration or test verification
Continuous Pulling Speed0.8 to 1.2 m/minSynchronized heavy hydraulic caterpillar puller; supplied reference requiring configuration or test verification
Existing application note: Offshore durability and strength or modulus retention apply to the selected laminate, exposure duration and test method. Fiber content includes its measurement basis. Original process references, with their existing values: Nitrogen pressure 0.05 MPa; Chemical moisture < 30 ppm; Metering pressure 12.0–15.0 MPa; Ratio tolerance ±0.2%; Impingement velocity > 100 m/s; In-line gel tracking; Cavity backpressure 1.8 MPa; Fiber volume > 82%; Die temp 160–195°C; Line speed 0.8–1.2 m/min. The existing process example uses 14.5 MPa metering. Confirm its actual pump, resin and measurement circuit; the value does not itself establish fiber wet-out or marine qualification. Confirm the configuration, material, test method and cycle endpoints before using reference values as acceptance commitments.
Shared equipment references

Core Equipment for This Solution

Equipment references are selected by their documented process. Main metering, auxiliary supply and alternative routes are not a single standard package.

Process configuration

Process controls and application checks

Evaluate these functions with the selected material, tooling and production brief. Finished-part results require their own acceptance evidence.

Defined reinforcement handling

Keep fiber guidance separate from the resin pump and mixing circuits.

Wet-out evidence

Verify the actual reinforcement fraction and impregnation rather than inferring quality from pressure.

Marine-system validation

Assess resin, fiber, connections and module performance under the intended exposure.

Related project brief

Related Projects

These are related application references. Compare the actual material, process and delivered modules; reported project figures are not acceptance results for another line.

Review Project
Planning questions

Frequently Asked Questions

Technical questions to establish the equipment scope, material window and validation plan.

Does a salt-spray duration establish offshore service life? +
No. Use the original specimen, coating/connection construction and test method, then assess the intended environment and failure criteria.
Can every listed fiber use the same settings? +
No. Fiber form, sizing, content and resin compatibility affect wet-out and die behavior. Validate the selected combination.
What information is needed for a preliminary configuration? +
Profile and connection drawings, fiber form/content basis, resin data, marine exposure, electrical requirements and line interfaces. Identify the equipment and interfaces to retain, plus the required test and acceptance documents.

Request an Offshore Marine Solar Frame Proposal

Share the following with your production brief: Profile and connection drawings, fiber form/content basis, resin data, marine exposure, electrical requirements and line interfaces. Our team will reply within one business day. Once requirements are clear, we provide a preliminary proposal within two business days.

Contact us

For how we handle your inquiry information, read our Privacy Policy.

Configuration review based on the application and material data Agreed equipment, interface and acceptance documentation Training and support defined for the supplied package
Haifeng Polyurethane Machinery on TikTok
Haifeng Polyurethane Machinery on Instagram
Haifeng Polyurethane Machinery on Facebook
Haifeng Polyurethane Machinery on X
Haifeng Polyurethane Machinery on LinkedIn
Contact Haifeng Polyurethane Machinery on WhatsApp
Haifeng Polyurethane Machinery on YouTube