Welding Standard Operating Procedure (SOP) and Process Accuracy Standards Banner background

Welding Standard Operating Procedure (SOP) and Process Accuracy Standards

This welding SOP defines materials, WPS requirements, fit-up tolerances, heat-input controls, inspection and leak testing for polyurethane equipment frames and piping.

Concept of stainless pipe butt-weld preparation with aligned clamped ends, a TIG torch and inspection tools

Haifeng Process Standards: Quick Reference

Welding quality in Haifeng polyurethane equipment directly affects frame rigidity and piping-seal reliability. For every 1 mm/m that frame-weld distortion exceeds the specified tolerance, the servo metering-pump mounting datum can shift by more than 0.05 mm during final assembly, indirectly affecting metering-ratio accuracy. Piping welds must pass a 0.02 MPa air-tightness test with no leakage.

Quick reference for key process parameters:

ParameterHaifeng StandardIndustry ReferenceRelated Equipment Accuracy
Transverse shrinkage per butt weld on frame square tube0.50–0.60 mm per weld (0.5 mm process allowance)Estimated by experienceServo installation-datum deviation after final assembly ≤0.5 mm
Longitudinal shrinkage rate of frame welds2–3 mm/m (process allowance)Estimated by experienceFrame straightness over full length ≤2 mm/m
Heat input for 316L stainless-steel piping≤1.5 kJ/mm≤2.5 kJ/mmWeld passes intergranular-corrosion requirements
Welding-current stability±1 A adjustment accuracy±3 APenetration consistency CV ≤5%
Weld reinforcement (pipe butt weld)0–2 mm0–3 mmSealing-surface flatness ≤0.1 mm
Pipe misalignment≤10% of wall thickness and ≤0.5 mm≤10% of wall thicknessSmooth internal transition with no turbulence dead zones
Piping air-tightness test0.02 MPa, no leakage for 30 min0.02 MPaPiping-system sealing meets requirements
Weld undercut depth≤0.5 mm; continuous length ≤100 mm≤0.5 mmFatigue life of pressure welds is maintained
Pre-weld cleaning area for stainless steel≥50 mm on both sides of bevel≥30 mmPorosity ≤0.5%
Interpass temperature for 316L≤150°C≤200°CAvoids extended dwell in the sensitization range
Tungsten-electrode tip angle15°–30° (sharp cone)30°–60°Concentrates arc heat and reduces HAZ width
Frame straightness after welding≤1‰ of full length and ≤3 mm≤2 mm/mMeets JB/T 11509 manufacturing-accuracy requirements

1. Scope

1.1 Application

This SOP applies to the following welding operations for Haifeng polyurethane equipment:

Welded ComponentTypical MaterialWelding MethodQuality Level
Square-tube frameQ235B / Q345BGMAW (MAG)ISO 5817 Level C
Stainless-steel material tanks and heads304 / 316LGTAW root pass + GMAW cap passISO 5817 Level B
Isocyanate / polyol feed piping316LAll-position GTAWISO 5817 Level B
High-pressure mixing-head piping316L / 17-4PHGTAWISO 5817 Level B
Temperature-control jacket piping304GTAWISO 5817 Level C

2. Pre-Work Preparation and Welding-Procedure Qualification

2.1 Welding-Procedure Qualification (WPQR) and WPS

All Haifeng welding work must follow a Welding Procedure Specification (WPS) qualified to ISO 15614-1. The WPS must include the following essential variables:

No.WPS VariableHaifeng Requirement
1Parent-material groupClassified according to ISO/TR 15608 (e.g., Group 1.1 carbon steel, Group 8.1 austenitic stainless steel)
2Welding processGTAW (141) / GMAW (135); specify whether pulsed
3Welding positionSpecify according to ISO 6947 (PA/PF/PC, etc.)
4Joint designBevel type and angle, root face, fit-up gap and tolerances
5Filler metalSpecify classification, size and batch; for 316L piping, prefer ER316L filler wire (Mo content ≥2.0%)
6Electrical parametersCurrent, voltage, welding speed and permitted ranges
7Shielding gasType, purity (≥99.99%) and flow rate
8Preheat / interpass temperatureCarbon steel ≥15°C; 316L interpass temperature ≤150°C
9Heat inputCalculated value and permitted upper limit

2.2 Welding-Equipment Accuracy Calibration

Equipment / ToolAccuracy RequirementCalibration Interval
Welding-power-source ammeter±1 A adjustment accuracyEvery 3 months
Welding-power-source voltmeter±0.1 V adjustment accuracyEvery 3 months
Heat-input data loggerSynchronized sampling of current, voltage and speed at ≥10 HzEvery 6 months
Infrared thermometer±1% of readingEvery 6 months
Weld gauge0.1 mm resolutionEvery 6 months
Bevel-angle gauge0.5° resolutionEvery 12 months

Haifeng welding power sources must provide constant-current and constant-voltage output modes, have a power factor ≥0.95, and support preset and stored welding parameters (at least 100 sets) for rapid changeover and traceability across product models.

3. Structured Welding Workflow

3.1 Pre-Weld Preparation and Material Control

3.1.1 Parent-Material and Filler-Metal Verification

Inspection ItemHaifeng StandardVerification Method
Parent-material certificateMatches material grade on the drawingVerify heat/batch number
Filler-metal classificationMatches the WPSCheck package markings
Filler-metal storageStore stainless-steel and carbon-steel filler metals in separate zonesVisual inspection
Filler-metal dryingFollow filler-metal manufacturer’s instructions, where applicableDrying log
Shielding-gas purity≥99.99% (Ar)Gas analysis certificate

3.1.2 Bevel Preparation and Cleaning

Stainless steel is extremely sensitive to surface contamination. Grease, moisture or oxide scale left before welding can decompose in the high-temperature arc, cause porosity or reduce weld corrosion resistance.

StepOperationAccuracy Standard
Bevel preparationMachine or plasma-cut, then grindBevel-angle deviation ≤±2.5°
Cleaning areaAt least 50 mm on each side of the bevelWipe with acetone or anhydrous ethanol
Oxide removalGrind with a dedicated stainless-steel wire brush to bright metalDo not use a carbon-steel brush
Fit-up gapSquare groove: 0–0.5 mm; V-groove: as specified in WPSCheck with feeler gauge
Misalignment≤10% of wall thickness and ≤0.5 mmWeld gauge

3.2 Tack Welding and Distortion Control

3.2.1 Tack-Weld Parameters

Tack welding is critical to controlling weld distortion and dimensional accuracy. Tack spacing must be 50–100 mm, tack length approximately 5–10 mm, and penetration should generally be controlled to within 0.8 mm to avoid stress concentrations during final welding.

Welded ComponentTack SpacingTack LengthPenetration Control
Square-tube frame (3–6 mm wall)80–100 mm8–10 mm≤1.0 mm
Stainless-steel piping (2–4 mm wall)50–80 mm5–8 mm≤0.8 mm
Longitudinal seam on tank shell100–150 mm10–15 mm≤1.5 mm

3.2.2 Welding-Distortion Pre-Compensation

Based on data validated by testing, Haifeng welding procedures use the following distortion pre-compensation strategy:

Weld-Joint TypeMeasured ShrinkageProcess Allowance
Transverse shrinkage of butt joint0.50–0.60 mm per weldAllow 0.5 mm for each transverse seam
Longitudinal weld shrinkageDouble-sided welds shrink more than single-sided weldsAllow 2–3 mm per meter of longitudinal weld
Frame fillet jointAdjust according to structural rigidityDetermine using trial-weld data

3.3 Welding Parameters and Heat-Input Control

3.3.1 Recommended GTAW Parameters for Stainless-Steel Piping

Recommended welding parameters for 316L stainless-steel piping commonly used in Haifeng equipment:

Pipe Wall Thickness (mm)Tungsten Diameter (mm)Filler-Wire Diameter (mm)Welding Current (A)Argon Flow (L/min)Nozzle Diameter (mm)
1.51.61.240–657–98.0 (#5)
2.01.6–2.41.6–2.055–858–109.5 (#6)
3.02.42.0–2.480–11010–1211.0 (#7)
4.02.42.4100–14010–1211.0 (#7)

Accuracy control: Welding-current adjustment accuracy must reach ±1 A, and voltage adjustment accuracy must be ±0.1 V. During welding, current fluctuation must not exceed ±3% of the set value.

3.3.2 Heat-Input Control (Critical Accuracy Parameter)

If austenitic stainless steel remains too long in the 450–850°C sensitization range, chromium carbides can precipitate and cause intergranular corrosion. Heat input must therefore be strictly controlled when welding 316L piping in Haifeng equipment that contacts isocyanate.

Welded ComponentHaifeng Heat-Input LimitIndustry ReferenceControl Measures
316L piping (wall thickness ≤3 mm)≤1.0 kJ/mm≤2.5 kJ/mmLow current, fast welding, pulsed mode
316L piping (wall thickness 3–6 mm)≤1.5 kJ/mm≤2.5 kJ/mmMultiple layers and passes; interpass cooling
304 tank shell≤1.5 kJ/mm≤2.5 kJ/mmSymmetrical welding and back-step sequence

3.4 Weld Inspection and Sealing Verification

3.4.1 Visual Weld Inspection

Inspection ItemHaifeng Standard (Level B Weld)Inspection Tool
Weld reinforcement0–2 mm (pipe butt weld)Weld gauge
Undercut depth≤0.5 mm; continuous length ≤100 mm; total undercut on both sides ≤10% of weld lengthWeld gauge
Misalignment≤10% of wall thickness and ≤0.5 mmWeld gauge
Surface porosityNot permitted (Level B)Visual inspection and 5× magnifier
Lack of fusion / incomplete penetrationNot permittedVisual inspection and penetrant testing
Weld-width uniformityDeviation ≤2 mmCaliper

3.4.2 Non-Destructive Testing

Test MethodApplicationAcceptance LevelInspection Rate
Penetrant testing (PT)Surface defects in stainless-steel pipingISO 23277 Level 2X100%
Radiographic testing (RT)Longitudinal and circumferential tank-shell weldsISO 10675-1 Level BAt least 20% sampling
Air-tightness testAll feed piping0.02 MPa for 30 min100%
Hydrostatic testTanks and pressure piping1.5 times design pressure100%

After welding piping joints, perform an air-tightness test at 0.02 MPa. The test passes if there is no leakage for 30 minutes. For the tightness test, reduce internal pressure to operating pressure; the test passes if there is no leakage for 30 minutes and the pressure drop does not exceed 0.02 MPa.

4. Core Welding-Accuracy Parameter Table

No.Accuracy CategoryParameterHaifeng StandardInspection ToolInspection Frequency
1Dimensional accuracyCut-length deviation for frame square tube±0.5 mmTape measure and square100% inspection
2Dimensional accuracyFrame diagonal deviation≤2 mm within a 3 m × 3 m areaLaser distance meter100% inspection
3Dimensional accuracyFrame straightness after welding≤1‰ of full length and ≤3 mmLevel and taut line100% inspection
4Dimensional accuracyPipe-joint misalignment≤10% of wall thickness and ≤0.5 mmWeld gauge100% inspection
5Process parameterWelding-current stability±1 A adjustment accuracyBuilt-in power-source meterReal-time monitoring
6Process parameterHeat input (316L piping)≤1.0 kJ/mm (wall thickness ≤3 mm)Heat-input data loggerRecord each pass
7Process parameterInterpass temperature (316L)≤150°CInfrared thermometerCheck each pass
8Weld qualityWeld reinforcement0–2 mmWeld gauge100% inspection
9Weld qualityUndercut depth≤0.5 mmWeld gauge100% inspection
10Weld qualityPorosity (RT)Not permitted for Level B weldsRadiographic testingSampling inspection
11Sealing performancePiping air-tightness test0.02 MPa / 30 min, no leakagePressure gauge and leak-detection solution100% inspection

5. Common Problems and Process Pitfalls

5.1 Frame-Weld Distortion Shifts Final-Assembly Datums

Symptom: After frame welding, the diagonal deviation exceeds tolerance, or final assembly reveals that the servo metering-pump mounting base is not flat. Extensive weld repair, cutting and grinding are required.

Root cause: Polyurethane foaming-machine frames have many welds and complex structures. Concentrated welding heat causes uneven shrinkage. In industry, foaming-equipment frames can have low welding accuracy, requiring local weld repair, cutting and grinding during final assembly and resulting in poor product consistency.

Solutions:

1. During cutting, allow for process shrinkage based on measured data (0.5 mm per transverse weld and 2–3 mm/m for longitudinal welds).

2. Use a symmetrical welding and back-step sequence to balance heat input.

3. After welding, check diagonals with a laser distance meter. If deviation exceeds 2 mm, investigate the cause and adjust the process.

4. Correct final-assembly datum deviation with shims. Do not use flame straightening.

5.2 Intergranular Corrosion in Stainless-Steel Pipe Welds

Symptom: Rust spots appear near pipe welds after several months, or piping passes the air-tightness test but begins leaking after a period of operation.

Root cause: If 316L stainless steel remains too long in the 450–850°C sensitization range, chromium carbides precipitate and deplete chromium at grain boundaries. Excessive heat input or uncontrolled interpass temperature is the main cause.

Solutions:

1. Strictly limit heat input to ≤1.0 kJ/mm for wall thickness ≤3 mm.

2. Use pulsed welding to reduce heat accumulation.

3. Check interpass temperature after every pass; it must be below 150°C.

4. Pickle and passivate the weld after completion to restore the surface passive film.

5.3 Poor Internal Pipe-Weld Profile Causes Material Retention

Symptom: The proportioning accuracy of isocyanate piping gradually drifts, or cleaning intervals become noticeably shorter.

Root cause: Excessive internal weld reinforcement or a concave weld profile creates dead zones where material can collect. Isocyanate may self-polymerize in these areas, gradually blocking the pipe and changing its effective flow area.

Solutions:

1. Use internal argon purging when welding piping to ensure a smooth root profile.

2. Limit internal weld reinforcement to 0–1 mm, stricter than the external-weld standard.

3. After welding critical piping, including the mixing-head inlet section, inspect the internal profile with a borescope.

4. Mechanically grind internal defects to a smooth transition and repassivate after grinding.

5.4 Insufficient Shielding Gas Causes Oxidation and Porosity

Symptom: Stainless-steel welds are black or show pronounced oxide colors, or RT reveals scattered porosity.

Root cause: Shielding-gas flow is insufficient, a gas lens is not installed, or wind interferes with the welding area during field welding. Oxidation of austenitic stainless-steel welds also reduces corrosion resistance.

Solutions:

1. Adjust gas flow according to plate thickness and nozzle diameter to protect the weld pool and heat-affected zone.

2. Install a gas lens to improve laminar shielding.

3. For field welding, set up a wind screen. Take additional protection measures when wind speed exceeds 2 m/s.

4. Pickle weld surfaces if oxidation exceeds a light-straw color.

5.5 Improper Flame Straightening Causes Secondary Damage

Symptom: Flame straightening is used after frame distortion, followed by abnormal local hardness or cracking.

Root cause: Straightening temperature is not controlled properly. For stainless steel, the flame-straightening temperature must not exceed 580°C. Use a neutral flame, hold it 3–5 mm from the workpiece and move it rapidly. Excessive temperature increases sensitization, while abrupt correction can introduce new residual stresses.

Solutions:

1. Strictly limit flame-straightening temperature for stainless steel to ≤580°C, monitored with temperature-indicating crayons.

2. Use gradual flame straightening. Avoid abrupt corrections with triangular or line heating.

3. Allow carbon-steel frames to cool naturally after flame straightening; do not water-quench.

4. After straightening, take sample hardness readings in the heated area. Hardness must not exceed 120% of the parent-material hardness.

5.6 Mixing Filler Metals Reduces Corrosion Resistance

Symptom: Carbon-steel or 304 filler metal is used instead of 316L filler metal. No obvious issue appears initially, but the weld preferentially corrodes over time.

Root cause: The difference in molybdenum content between 316L (2.0–3.0% Mo) and 304 (no Mo) results in substantially different corrosion resistance in chloride-containing and acidic environments. Corrosion requirements from isocyanate and additives make it essential to match filler-metal corrosion resistance to that of the parent material.

Solutions:

1. Maintain a filler-metal issue log. For welding 316L piping, issue ER316L wire against the WPS.

2. Before welding, use a spectrometer to sample and verify that filler-metal Mo content is ≥2.0%.

3. Store stainless-steel and carbon-steel filler metals in physically separate, clearly labeled locations.

4. Cut out and rework any weld made with unauthorized substitute filler metal.

Discuss Your Polyurethane Production Requirements

Share your application, material system, target output and automation requirements. Haifeng's engineering team can help you review equipment and production-line options.