Cold Storage Envelope Spray Solution Banner background

Cold Storage Envelope Spray Solution

Plan hydraulic PU spraying for high-wall cold-storage insulation with defined access and coating build.

Process configuration

Seamless Thermal Envelopes for High-Bay Cold Storage Facilities

High-bay cold-store spraying requires the insulation system, substrate, hose route and work access to be planned together. Field spraying and prefabricated panels solve different construction needs. A nominal pumping lift or daily area does not establish the gun conditions, finished thermal bridges or floor-load capacity.

Defined supply scope

Define the spray rig, heated hoses, access/lifting equipment, surface preparation and protection layers. Complete-envelope thermal, moisture and structural requirements remain part of the building design.

Inputs for process selection

Wall/roof area, height, substrate, insulation thickness, protective system, hose/access plan and working shifts.

Equipment scope, retained factory interfaces and acceptance are agreed for the selected material and part. Define the spray rig, heated hoses, access/lifting equipment, surface preparation and protection layers. Complete-envelope thermal, moisture and structural requirements remain part of the building design.

Production route

Cold Storage Envelope Spray Workflow

Survey the envelope and access → Prepare and condition → Spray and measure build → Finish and inspect. Define preparation, filling, cure and output timing separately for the selected configuration.

01

Survey the envelope and access

Review substrate, height, penetrations and work-area arrangements.

02

Prepare and condition

Establish primer, materials, hose routing and operating conditions.

03

Spray and measure build

Validate gun delivery and application thickness at the actual elevation.

Process configuration

Reference Solution Engineering Envelope

Existing configuration and test references. Equipment settings, material results and finished-assembly results are separate; apply each value only to its documented configuration and conditions.

ParameterValue / UnitApplicable Configuration / Conditions
Maximum Vertical Pumping LiftUp to 60 metersContinuous hydraulic proportioner with reinforced heated lines
Fluid Dispensing Flow Output4.0 to 14.0 kg/minContinuous dual-gun impingement application
Core Foam Compressive StrengthGreater than or equal to 180 kPaASTM D1621 test on high-density rigid polyurethane core
Daily Single-Rig Application OutputGreater than or equal to 2,500 m²Double-shift continuous field spraying across high walls
Primary Inline Heating Power18 kW Total ElectricalMulti-stage anti-crystallization cast-aluminum heating blocks
Finished Surface Flatness VarianceWithin 5.0 mmPost-spray mechanical wire scraping across 2m span
Existing application note: Spray output and coverage depend on thickness, density, material use, overspray and spraying duty. Vertical lift, hose length and gun pressure are sized for the complete circuit. Foam fire performance and installation acceptance are assessed separately. Original process references, with their existing values: Surface moisture < 8%; Primer dry film 50–80 µm; confirm for selected material and tooling; Working pressure 16.0–18.0 MPa; Vertical lift up to 60 m; confirm for selected material and tooling; Fluid temp 48–52°C; Heaters 18 kW cast-aluminum; confirm for selected material and tooling; Pass thickness 35–40 mm; Total thickness 150 mm; confirm for selected material and tooling; Surface variance < 5 mm; Compressive strength ≥ 180 kPa; confirm for selected material and tooling. Supplementary references: substrate adhesion > 0.2 MPa; material circuits stated as 17.5 MPa and 18.0 MPa in different passages; gun temperature 50°C ± 1°C; cream time 3 seconds; outdoor ambient reference 5°C. Resolve the circuit/working-point distinction and verify gun-end conditions; these values do not establish zero pressure loss or full cure. The earlier site examples mention 45m elevation and a 45-degree spray pattern. Confirm the actual gun/nozzle and operating conditions; these do not establish zero pressure loss. Confirm the configuration, material, test method and cycle endpoints before using reference values as acceptance commitments.

Core Equipment for This Solution

Equipment references are selected by their documented process. Main metering, auxiliary supply and alternative routes are not a single standard package.

Process controls and application checks

Evaluate these functions with the selected material, tooling and production brief. Finished-part results require their own acceptance evidence.

Elevation-specific delivery

Measure gun-end temperature and pressure with the installed hose path.

Comparable productivity

State shifts, thickness, preparation and good-area counting with any daily-output figure.

Envelope detail planning

Treat penetrations, joints and thermal bridges as assembly details rather than automatically eliminated defects.

Related Projects

These are related application references. Compare the actual material, process and delivered modules; reported project figures are not acceptance results for another line.

Review Project
Planning questions

Frequently Asked Questions

Is spraying always preferable to insulated panels? +
No. Compare access, geometry, substrate condition, refurbishment needs and complete-envelope requirements.
Does a lift rating prove stable spray conditions at height? +
No. Verify pressure loss, temperature and spray behavior under the actual flow, hose and ambient conditions.
What information is needed for a preliminary configuration? +
Wall/roof area, height, substrate, insulation thickness, protective system, hose/access plan and working shifts. Identify the equipment and interfaces to retain, plus the required test and acceptance documents.

Discuss Your Production Goals

Share the following with your production brief: Wall/roof area, height, substrate, insulation thickness, protective system, hose/access plan and working shifts. Our team will reply within one business day. Once requirements are clear, we provide a preliminary proposal within two business days.

Contact us

For how we handle your inquiry information, read our Privacy Policy.

Configuration review based on the application and material data Agreed equipment, interface and acceptance documentation Training and support defined for the supplied package
Haifeng Polyurethane Machinery on TikTok
Haifeng Polyurethane Machinery on Instagram
Haifeng Polyurethane Machinery on Facebook
Haifeng Polyurethane Machinery on X
Haifeng Polyurethane Machinery on LinkedIn
Contact Haifeng Polyurethane Machinery on WhatsApp
Haifeng Polyurethane Machinery on YouTube