Deep-Freeze Warehouse Insulation in Kazakhstan project reference: Site-applied PU insulation for the specified cold-storage structure and protective details.

Project Reference and Configuration

Illustration notice. Process illustrations are not verified photographs of this installation.

Project reference basis. Figures and configuration details are reported in the supplied project brief. They are reference values for the stated application, rather than verified acceptance results or a guarantee for another installation. Confirm the source records, material, tooling, operating schedule and test method when assessing a comparable project.

This project reference describes site-applied PU insulation for the specified cold-storage structure and protective details.

Configuration and numerical values are reproduced from the supplied project brief for discussion. Original production, inspection and acceptance records have not been verified; these values do not establish certification or performance for another configuration.

Configuration Listed in the Project Brief

Solution ModuleTarget AreaCore MaterialMain ProcessTypical Operation Mode
Cold Storage & RefrigerationDeep-Freeze Warehouses (-35°C)PIR (45 kg/m³)In-Situ High-Pressure SprayingHigh-Elevation Scaffolding Setup

Equipment References in the Project Brief

The supplied brief lists the following equipment references. Model identities, quantities and the actual delivery scope follow the original equipment schedule.

1. Heavy Hydraulic Spray Machine: Primary fluid heating, hydraulic ratio metering & extreme-pressure delivery
2. 90m Multi-Zone Heated Hose Line: Maintaining precursor chemical temperature across 24m vertical elevations
3. High-Velocity Impingement Spray Gun: Impingement mixing and fan atomization on vertical concrete and steel
4. Pneumatic Chemical Transfer Skids: Feeding viscous chemicals from 200L drums to the proportioner
5. Master Automation PLC Control Cabinet: Multi-zone temperature regulation, ratio monitoring & emergency interlocks

Installation, training, warranty and service arrangements follow the project agreement; durations in this brief are references.

EquipmentModelQtyFunction
Heavy Hydraulic Spray MachineHF-SPF-H2001 UnitPrimary fluid heating, hydraulic ratio metering & extreme-pressure delivery
90m Multi-Zone Heated Hose LineHF-HOSE-90M1 SetMaintaining precursor chemical temperature across 24m vertical elevations
High-Velocity Impingement Spray GunHF-GUN-AIRLESS2 UnitsImpingement mixing and fan atomization on vertical concrete and steel
Pneumatic Chemical Transfer SkidsHF-PUMP-2:12 UnitsFeeding viscous chemicals from 200L drums to the proportioner
Master Automation PLC Control CabinetHF-PLC-MOBILE1 SetMulti-zone temperature regulation, ratio monitoring & emergency interlocks

Project Reference Values

≤0.019 W/(m·K)
Reference: Thermal-Conductivity
Project-brief reference; original records pending. The brief lists this conductivity value and a 0.028 W/(m·K) baseline. Confirm formulation, density, aging, test temperature, specimen and original report.
0 reported incidents
Reference: Joint/Operation
Project-brief reference; original records pending. The brief lists no joint-splitting or icing incidents during a 12-month period at −35°C. Confirm the monitored scope and records; this is not a long-term failure-free assurance.
1,200 m²/day
Reference: Daily-Application
Project-brief reference; original records pending. The brief lists 1,200 m² per day versus a 350 m² baseline. Confirm thickness, working hours, staffing and site access before comparing output.