Решение для конструктивного заполнения рам модулей HJT
Координация позиционирования рамки солнечного модуля по четырём кромкам, дозирования двухкомпонентного клея, сборки углов и отдельно контролируемого этапа обработки с отверждением без нагрева.
Buffer-Free Fast Structural Framing for Large-Format Dual-Glass Modules
Coordinate four-edge solar module frame positioning, two-component adhesive dispensing, corner assembly and a separately verified green-cure handling stage. The described scope includes frame positioning and pressing, proportioning, multi-head dispensing and conveyor interfaces. Adhesive, extrusions, glass, handling fixtures and cure residence are confirmed for the module. This assembles existing frames; it is distinct from manufacturing composite profiles.
Изделие, материал и оснастка
The described scope includes frame positioning and pressing, proportioning, multi-head dispensing and conveyor interfaces. Adhesive, extrusions, glass, handling fixtures and cure residence are confirmed for the module. This assembles existing frames; it is distinct from manufacturing composite profiles.
Производительность и приёмка
Рассмотрите все этапы подготовки, дозирования, отверждения, обращения и контроля. Для результатов по материалам и компонентам требуются отдельно согласованные условия испытаний.
Map frame positioning, clamping, multi-head dispensing and the green-strength buffer as separate stages. Structural adhesive, glass/frame preparation and final cure require their own validation; an early handling strength is not final bond qualification.
Turnkey Automated Dual-Glass Framing Workflow
Приведённая последовательность процесса служит справочной конфигурацией. Параметры температуры, давления, производительности и отверждения подтверждаются для выбранного материала и оснастки.
Dual-Glass Infeed & Automatic Centering
Configured reference: Laminated G12 dual-glass panels transfer via motor rollers into the machine bed, centered within ±0.5 mm by pneumatic aligning pushers.
4-Corner Synchronous Hydraulic Pressing
Configured reference: Four servo-hydraulic cylinders drive corner keys into frame extrusions under 50 kN force, squaring the frame around glass edges.
Closed-Loop Two-Component High-Pressure Metering
Configured reference: Servo gear pumps displace structural polyol and modified isocyanate at 9.0 MPa under Coriolis mass flow measurement within ±0.2% accuracy.
Технические характеристики эталонного решения
Значения перенесены из предоставленного технического задания на конфигурацию. Свойства материалов и показатели готовой продукции являются отдельными целями валидации, а не общими гарантиями оборудования.
| Параметр | Значение / единица измерения | Применимая конфигурация / условия |
|---|---|---|
| Single-Module Framing Tact Time | Less than or equal to 25 seconds | Synchronous 4-corner pressing and 4-head cavity grouting; supplied reference requiring configuration or test verification |
| Handling Green Cure Duration | Less than or equal to 180 seconds | Room-temperature chemical crosslinking (25°C ambient); supplied reference requiring configuration or test verification |
| Combined Chemical Injection Rate | 15.0 to 60.0 g/s | Four independent servo-controlled dynamic mixing channels; supplied reference requiring configuration or test verification |
| Cured Matrix Lap Shear Strength | Greater than 12.0 MPa | Material/joint target; appropriate substrate-specific test needed. ASTM D1002 metal-to-metal specimens do not directly establish aluminum-to-glass bond performance. |
| Module Mechanical Wind/Snow Load | Up to 8,500 Pa static load | reported under IEC 61215-2 mechanical load sequence; supplied reference requiring configuration or test verification |
| Factory Floor Space Savings | Up to 1,500 m² saved | Elimination of multi-tier 4-hour silicone curing buffers; supplied reference requiring configuration or test verification |
Core Advantages of Haifeng HJT Framing Systems
Инженерные функции и интерфейсы, разработанные для указанного изделия и системы материалов.
Frame positioning
Verify squareness, datum and corner assembly for the actual module.
Adhesive supply
Prepare and meter the chosen material with defined substrate conditions.
Head balance
Check each path and combined output through starts, stops and purge.
Supported green cure
Provide the agreed residence and handling limit before final cure.
Связанные проекты
The HJT upgrade is a project-specific framing reference; it does not establish every frame substrate, adhesive or final bond performance.
Часто задаваемые вопросы
Технические вопросы для определения состава оборудования, диапазона материалов и плана валидации.
How does green strength differ from final adhesive cure?
Can different frame substrates be considered?
How is delivery balanced across four heads?
How are interruption and purge limits configured?
Какие исходные данные нужны для этой конфигурации?
How should the framing takt and green-cure buffer be coordinated?
Request an HJT Module Structural Framing Proposal
Share the following for this application: Module/frame sections, corner/joint gap, adhesive, combined/per-head shot, clamping, handling load, buffer and final bond tests. Our team will reply within one business day. Once requirements are clear, we provide a preliminary proposal within two business days.